Brief

"On 18/12/2024, the Environment Agency (EA) issued an update regarding SR2022 No 3: construction, demolition and excavation waste transfer station. This standard rules permit allows operations of a specific type of waste transfer station under certain conditions, with associated charges for application and annual subsistence."

This standard rules permit allows you to operate a construction, demolition and excavation waste transfer station.
You can apply for this standard rules permit if:

your activity meets the rules set out in the permit

you can manage the potential risks as set out in the generic risk assessment

The charges for applying for this standard rules permit are:

£2,641 for a new standard rules permit application

£792 for a minor variation to the permit

£2,529 to transfer the permit

£1,585 to surrender the permit

There is also an annual subsistence charge of £1,920 for the standard rules permit.
You can get advice before you apply for a permit.
How to apply for an environmental permit.

This permit replaces:

SR2008 No 10 75kte inert and excavation waste transfer station

SR2009 No 5 inert and excavation waste transfer station below 250kte

If you cannot comply with the new standard rules permit you will need to apply to vary your permit into a bespoke permit. You must apply within 3 months of the date the standard rules was published (18 December 2024).

Highlights content goes here...

Purpose

The purpose of this standard rules permit is to allow construction, demolition, and excavation waste transfer stations to operate within specific guidelines. The permit is designed to regulate activities that meet certain rules and risk management criteria. This permit aims to ensure environmental protection by controlling the handling and disposal of waste.

Effects on Industry

This update has significant implications for industries involved in construction, demolition, and excavation activities. The new standard rules permit charges are substantial, with fees ranging from £792 for minor variations to £2,641 for a new permit application. Additionally, an annual subsistence charge of £1,920 applies to all permits. This may lead to increased operational costs and potentially affect profit margins for companies operating in these sectors. The replacement of previous permits (SR2008 No 10 and SR2009 No 5) with the standard rules permit also means that existing businesses must adapt to the new regulations or risk losing their permit.

Relevant Stakeholders

The following stakeholders are directly affected by this update:

  1. Construction, demolition, and excavation companies operating waste transfer stations.
  2. Businesses involved in waste management and disposal services.
  3. Local authorities responsible for environmental regulation and permitting.
  4. Environmental agencies overseeing compliance with the new standard rules permit.

Next Steps

To comply with this update, stakeholders must take the following steps:

  1. Review existing permits (SR2008 No 10 and SR2009 No 5) to determine if they meet the new standard rules permit criteria.
  2. Apply for a new standard rules permit or minor variation within the specified timeframe.
  3. Pay applicable fees and charges for permit applications, variations, transfers, and surrenders.
  4. Ensure compliance with the generic risk assessment and manage potential risks associated with waste transfer station operations.

Any Other Relevant Information

The publication date of the standard rules permit (18 December 2024) serves as a deadline for existing businesses to adapt to the new regulations or apply for a bespoke permit if they cannot comply with the standard rules. This information is essential for stakeholders to plan and prepare accordingly, as failure to comply may result in permit revocation or non-compliance fines.

Environment Agency (EA)

Quick Insight
RADA.AI
RADA.AI
Hello! I'm RADA.AI - Regulatory Analysis and Decision Assistance. Your Intelligent guide for compliance and decision-making. How can i assist you today?
Suggested

Form successfully submitted. One of our GRI rep will contact you shortly

Thanking You!

Enter your Email

Enter your registered username/email id.

Enter your Email

Enter your email id below to signup.

Enter your Email

Enter your email id below to signup.
Individual Plan
$125 / month OR $1250 / year
Features
Best for: Researchers, Legal professionals, Academics
Enterprise Plan
Contact for Pricing
Features
Best for: Law Firms, Corporations, Government Bodies